哪位前辈能详细介绍一下这些MRP CODE的含义啊

哪位前辈能详细介绍一下这些MRP CODE的含义啊

MRP Order Code


MRP Order Code Description


A

Planned discrete or lot for lot. Can be overridden by max, min or multiple quantity.


B


Order point planning. Handled by the order proposal report. Order point qty needed.


C


Order up to planning. Handled by the order proposal report. Order point needed.


D

Fixed order qty planning. Lot size, max, min or multiple quantity is needed.


E


Least unit cost planning. Order qty calculated using setup cost and carrying rate.


F


Part period balancing planning. Order qty calculated using setup cost and carrying rate.


G


Period order qty planning. Accumulates the gross requirements for the number of days given.


K



Blow through planning. No additional fields are required.


M



Manually planned. Demands for component parts are not generated.


N



Next Level Demand.


O



Master schedule level 0 part.


P



Phantom part planning. No additional parts are required.


T



Master schedule level 0 phantom part.

---------------