哪位前辈能指教一下下面各MRP CODE的含义啊

MRP Order Code


MRP Order Code Description


A

Planned discrete or lot for lot. Can be overridden by max, min or multiple quantity.


B


Order point planning. Handled by the order proposal report. Order point qty needed.


C


Order up to planning. Handled by the order proposal report. Order point needed.


D

Fixed order qty planning. Lot size, max, min or multiple quantity is needed.


E


Least unit cost planning. Order qty calculated using setup cost and carrying rate.


F


Part period balancing planning. Order qty calculated using setup cost and carrying rate.


G


Period order qty planning. Accumulates the gross requirements for the number of days given.


K



Blow through planning. No additional fields are required.


M



Manually planned. Demands for component parts are not generated.


N



Next Level Demand.


O



Master schedule level 0 part.


P



Phantom part planning. No additional parts are required.


T



Master schedule level 0 phantom part.


---------------
来自伟创力电子(常州)的专业团队
We find a way to support you
xiexie

等我有空啊。。。。

等我有空做一个!

先贴一些看看

我找了个英文版的,为了大家看的清楚翻成了中文,先翻了一部份;累死了,我看还是先休息一会儿。。。

有问题请提出来我们讨论。。。

附件: 您所在的用户组无法下载或查看附件

看看这个可否?

我找了个英文版的、翻译了一部份,大家看看怎么样啊?多提意见、多交流啊。。。

附件: 您所在的用户组无法下载或查看附件

回复 5楼 unitprice 的帖子

我们公司目前用到了A/G/P,一般都是用A;
P是用于虚拟件,也就是在跑MRP的时候,这个物料不会产生物料的需求;或者在生成SO的时候,这个物料是不会出现出现在物料清单中的,而会把这个物料的BOM中的零部件显示出来;
G是用于MRP计算过程中,对于采购件,如果设置成A,那么物料的需求是针对于DEMAND(CO/FORECAST/SAFETY STOCK ETC)一一对应的,也就是说一条DEMAND生成一条SUPPLY记录。但是实际的采购业务中,可能会把一段时间的采购需求一起下订单,比如一天、一个星期,不同的公司,不同的采购有不同的要求,那么我就要把MRP CODE=G,并且设置COVRT TIME=7,(表示把7天内的采购申请汇总成1条采购申请)